Rendering of the northeast entry of the Masjid & Ghusl Center
News & updates

Current happenings

Stay informed about Al-Maghfirah Cemetery’s recent activities, events and developments.

Latest · August 2026

Phase 2 campaign launches on LaunchGood

With the construction contract signed, the association opened a LaunchGood campaign to fund the masjid and burial washing (ghusl) center — the final major phase before the cemetery can begin serving families.

With Allah’s grace and years of community support, Phase 1 — roughly five acres of burial grounds with nearly 5,000 lots, roads, parking, stormwater improvements and hundreds of evergreen trees — is complete and paid for. Phase 2 builds the masjid, ghusl center and supporting facilities designed by LSE Architects; once it is finished, Al-Maghfirah will be ready to begin burials, in sha’ Allah.

  1. August 2026

    Phase 2 campaign launches on LaunchGood

    With the construction contract signed, the association opened a LaunchGood campaign to fund the masjid and burial washing (ghusl) center — the final major phase before the cemetery can begin serving families.

  2. July 2026

    Construction contract signed for the Masjid & Ghusl Center

    The association signed the construction contract for Phase 2: the ghusl facility, prayer area, community hall and service offices designed by LSE Architects.

  3. June 2025

    Phase 1 complete — and fully paid

    Despite years of challenges and lawsuits, Phase 1 was finished and paid for with $1.4 million contributed by the Muslim community: about five acres of prepared burial grounds with nearly 5,000 lots, internal roads, paved parking, stormwater management and hundreds of evergreen trees planted as a natural boundary.

  4. June 11, 2025

    Asphalt base paving and pond work

    Things are moving along well, alhamdulillah. The asphalt base was paved, with final paving scheduled after the stormwater pond work is done.

  5. May 28, 2025

    Hauling in pond materials

    Concrete was poured and crews hauled in materials for the stormwater pond while waiting for the next available paving date.

  6. May 2025

    Funeral center design finalized

    LSE Architects presented the design for the Al-Maghfirah funeral center — ghusl rooms, a prayer hall, offices and parking — and the association met contractors on site on May 22, 2025.

  7. March 2025

    Site work begins

    Crews began earthwork and grading, followed by the internal road network and parking areas that were paved in the early summer.

  8. October 8, 2024

    Ceremonial groundbreaking

    After a decade of delays, the community broke ground in Castle Rock Township. The ceremony was covered by KSTP, WCCO/CBS, KARE 11, FOX 9 and Sahan Journal.

  9. August 2022

    Township approves the conditional use permit

    Castle Rock Township granted Conditional Use Permit 2022-0002, allowing the cemetery together with ghusl (ritual washing) and prayer facilities on the land.

  10. February 2016

    Court rules the cemetery must be allowed

    A Dakota County judge ruled that Castle Rock Township must allow the Islamic cemetery, the first major legal victory in a long fight for approval.

  11. 2014

    The land is purchased

    The community bought 72 acres of farmland at 1120 220th Street West in Castle Rock Township — and paid for it in full.

Videos

Watch the coverage and our updates

Groundbreaking held for Minnesota's first all-Muslim cemetery KSTP 5 Eyewitness News · October 2024
Twin Cities Muslim community celebrates groundbreaking of Al-Maghfirah Cemetery WCCO · CBS Minnesota · October 2024
Castle Rock approves use of Muslim cemetery in Farmington FOX 9 · 2022
Al-Maghfirah Cemetery — short clip Al-Maghfirah Cemetery on YouTube

From the grounds

1:35
An update from the grounds A walk through the site, the funeral center design and drone footage of the finished Phase 1 roads.
9:07
Why Al-Maghfirah? Why Minnesota’s Muslims need a cemetery of their own — and what the community is building.
0:32
Earthwork begins — March 2025 Dozers grading the first five acres of burial grounds.
0:42
Site work — April 2025 Excavators and haul trucks shaping the roads and parking areas.
On TikTok

The history of Al-Maghfirah: 12 years in the making

From the beginning of the journey twelve years ago, through obstacles and legal challenges, to Phase 1 complete and the final phase now under way.

Watch on TikTok Follow @al_maghfirah_cemetery_mn